Location: Meridian Grand, Advent Way, London N18
Investigative commercial EICR work across 16 functional areas, followed by urgent remedial planning and an 18-hour shift to address inherited electrical risks without disrupting the venue's next-day service.
Meridian Grand is a live events venue where electrical inspection and remedial work had to be planned around the operational calendar. Wire Now's investigative EICR scope covered 16 tenant and functional areas and combined visual inspection with instrumented testing. The inspection record identified unsafe inherited work, including an exposed service head recorded as C1 and distribution-board issues recorded as C2. To avoid disruption to the following day's venue service, the Wire Now team completed an 18-hour remedial shift.
The venue had inherited electrical work that required a systematic condition assessment. Because Meridian Grand had a scheduled service the next day, any urgent intervention also needed a controlled access, isolation and temporary-supply strategy.
The public case study describes the condition of the installation, not the identity or conduct of any previous contractor.
The invoiced inspection scope covered 16 tenant and functional areas. It combined a visual condition assessment with the measurements needed to understand the installation rather than relying on a surface-level check.
The records included a C1 exposed service-head risk and C2 observations involving mixed-manufacturer protective devices, damaged distribution-board enclosures and incoming cabling without adequate mechanical and fire-resistant protection.
The signed remedial scope included load calculations, a discrimination study, 18-circuit redesign drawings, RAMS, permits and a temporary-supply strategy. It also covered two critical TPN distribution-board replacements, type-approved protective devices and improved cable termination and containment.
Wire Now completed an 18-hour shift so the urgent work could be carried out without disrupting Meridian Grand's next-day service. That outcome depended on connecting the inspection evidence to a planned remedial sequence, rather than treating the EICR as a report-only exercise.
For facilities and venue teams, the lesson is practical: identify critical loads and operating windows before testing, then agree how C1, C2 and further-investigation findings will be controlled and closed out.
18-hour remedial shift completed ahead of the venue's next-day service
View case study →
View case study →
View case study →
Working on a tender or PQQ?
Download our pre-qualification pack and accreditations.
Already have drawings or photos?
Upload them with your quote request for a faster response.
Let's discuss your requirements and deliver a solution that works.